Latest Progress
The project has now commenced the commissioning phase of the project cycle. The majority of the civil construction works, mechanical and electrical installations are complete within the treatment building. The mains power supply has been connected and the remaining pipelines are being laid around the external perimeter of the buildings. The concrete structures are tested for water tightness and we can begin to move water through the different areas of the plant.
Initially all channels and tanks are flushed to remove any construction dust or debris. Filter media (sand and anthracite) is loaded into the filters and this is washed repeatedly until clean. All pipelines are pressure tested and flushed with water. All pumps are tested at their designed maximum and minimum flow rates. The emphasis turns towards testing each item of equipment in turn, systematically checking that each process unit is functioning correctly and then we will test the plant elements in automatic mode. On completion, in normal operation the works will be entirely run through computer systems with on site personnel carrying out regular checks and only intervening in exception when problems occur.
All the chemical dosing equipment will be commissioning using water initially to ensure it is working correctly before any actual chemicals are used, again to minimise the risk of working with these substances.
This phase of the project requires careful management to ensure all site personnel and visitors are safe. Permit systems are used for accessing different areas particularly where there is water flowing, electricity or confined spaces. All the treatment works activities are managed by a Commissioning Manager and his team of commissioning engineers. Communication between parties is achieved by using a dedicated channel on the site wide radio system.

