Glencorse Water Treatment Works - Midlothian
Scottish Water is building a new water treatment works at Glencorse in Midlothian, as part of the Edinburgh Drinking Water Project; a strategic programme of capital investment to build a new water treatment works (WTW) and replace ageing mains and storage tanks providing water to Edinburgh and surrounding areas.
Our aim is to facilitate the city’s continued expansion and improve the quality of drinking water in Edinburgh. It will also allow us to provide 21st century water treatment facilities, to meet strict European guidelines on drinking water quality.
The website is split into sections and can be navigated via the menu on the left hand side of the page.
Latest Project News
Fairmilehead Pipelines Update – 7th December 2011
December 2011
The tunneling works under Frogston Road West are being completed through harder rock than expected. Unfortunately, this has delayed the completion of tunneling operations. In turn, this has postponed the start of the remaining re-lining works.
All traffic management will be removed and excavations back-filled prior to the Christmas and New Year holiday period.
January - April 2012
The remaining sections of pipe re-lining within Biggar Road will be carried out together with final pipework connections.
During these works, temporary traffic management arrangements will be in place. A traffic contra-flow from the roundabout at Lothianburn will provide a safe working area along Biggar Road. Similar to work carried out in 2011, traffic management at Frogstone Road West will prevent a left turn into Biggar Road. These works will be removed as soon as pipework alterations are completed.
Alnwickhill, Liberton Park Update – 6th December 2011
Further to discussions with Liberton Association and City of Edinburgh Council Parks Department we have created a temporary access into Liberton Park from Alnwickhill Road.
The gaps in the existing boundary walls of the Water Treatment Works will be re-instated by Christmas.
Creation of a new footpath together with drainage works and re-seeding will continue throughout the spring 2012. To ensure proper growth of the new grass, the existing temporary fencing will remain in place until summer.
Fairmilehead Pipelines Update – 22nd September 2011
A major part of the Glencorse Project has been connecting the new Water Treatment Works to the existing water distribution network in the City. This has involved laying 15,000 metres of new pipelines through the Midlothian countryside as well as a programme of work in the Fairmilehead and Alnwickhill areas of Edinburgh.
Currently there are two large (30” and 33” diameter) pipes within Biggar Road which carry water from the reservoirs to the South of Edinburgh into Fairmilehead WTW where it is treated and made safe to drink. These two pipes were laid in 1904 and 1952. As part of the Glencorse project, rather than laying new pipes within Biggar Road, Scottish Water are re-using these two pipes and making them fit to carry the clean, treated water from Glencorse WTW to customers’ taps in Edinburgh. This approach avoids very disruptive pipelaying up the full length of Biggar Rd from the A720 city bypass to Fairmilehead WTW
Below is an outline of the work completed near Fairmilehead and the work still to be done.
Stage 1 (November 2010 to Feb 2011) – COMPLETED
Initial investigation work and utility surveys. Due to age of the existing pipes, extensive work had to be carried out to establish their depth and position in the road. Biggar Road also has a large number of other buried services such as gas, electricity and telecoms. During this stage we also removed an old flow monitoring device close to the crossroads (pictured below).
Stage 2 (March to June 2011) – COMPLETED
Investigation for pipeline rehabilitation. Part of this stage involved draining the water from the pipes and sending a camera up to film the condition of the insides of the pipes. We also cut out small sections of pipe in order to complete tests. Throughout this it was vital that we avoided disrupting the supply of water to customers’ taps.
Stage 3 (July to September 2011) – COMPLETED
Cleaning and testing of pipes. The pipe laid in 1952 was jet-washed and swabbed in sections to make it ready to carry treated water. Another camera was then used to film the inside of the pipe.
Stage 4 (August to October 2011) – Underway
Cross connections and re-lining on Biggar Road. A plastic liner has been pulled through the existing 1904 pipe. Cross connection pipework is also underway within the junction with Frogston Road West and Biggar Rd.
Stage 5 (October to November 2011) – To be completed
Tunnelling Works. A new section of pipe needs to be laid from the crossroads into Scottish Water’s compound. To minimise disruption this will be done via a tunnelling exercise.
Stage 6 (October to December 2011) – To be completed
Re-lining work at Fairmilehead Junction. This work was initially planned to finish in November 2011, due to ground conditions and existing services within the road, completion of the work will be extended one month.
Stage 7 (January to February 2012) – To be completed
Re-instatement of Biggar Road. To minimise traffic disruption over the festive period, final re-instatement work will be carried out early in 2012.
A similar update on work in the Alnwickhill area will be provided in coming weeks.
Now You See It……Soon You Won’t - 10th August 2011
Thousands of tonnes of soil are currently being moved in order to make the new Glencorse Water Treatment Works (WTW) become all but invisible to passers-by. Clever contouring of the landscape will see Scottish Water’s £130m development blend seamlessly into the backdrop of the Pentland Hills.
Already in place is Scotland’s largest green roof which covers the treatment building and the Clear Water Tank is about to get the same treatment. The 90 million litre water storage tank has just been covered with soil (this operation is pictured underway below). The huge tank will then be seeded with the same wild flower grass mix that can be found on the roof of the treatment building.
The project team have worked closely with local residents and Pentland Hills Regional Park to ensure that the new WTW will have minimal visual impact.
Click here to view the latest pictures and see how the project has progressed over the last 3 years.
Pipeline Activities on Biggar Road – 12th July 2011
Important work is currently underway on Biggar Road in Edinburgh. This is part of our 12 month programme of work that has been agreed with City of Edinburgh Council Roads Authority. There will be excavations on the road between now and November to allow essential pipe cleaning and re-lining work to take place.
We apologise for the inconvenience while we complete this crucial work.
Glencorse on Film - 9th June 2011
The Glencorse Project Team were delighted to assist Learning & Teaching Scotland with a new online resource about Scottish Engineering.
Wendy French of Learning and Teaching Scotland said;
"Engineering provides a rich, stimulating and challenging context for learning. The STEM Central website provides learning journeys created by teachers, starting from the experiences and outcomes, which make use of innovative, exciting projects such as Scottish Water's Glencorse WTW. The learning journeys that have been shared for the water treatment context highlight some of the innovative features of the Glencorse project such as the hydro power generator.
"By providing real life examples for teachers and videos introducing the different learning contexts, we hope young people will be given learning experiences which help them to understand more about engineering and its importance to our society."
Kenny Naylor and Lynsey Tweedlie from the project feature in the video. Click here to visit the STEM website and see the video which shows previously unseen footage inside the Water Treatment Works and the 90 million litre Clear Water Tank.
Glencorse Work within Scottish Water Complex – 8th June 2011
As part of the process to bring clearer, fresher drinking water to Edinburgh, the next phase of work within the Scottish Water complex at Fairmilehead is about to begin.
This essential work will be carried out in 4 phases and will run from Monday 13 June to mid August. During the work, up to 38 parking spaces will be unavailable to staff.
In order to minimise disruption to employees located on the site of our national Customer Contact Centre, this work has been planned to coincide with the summer months, when many employees will be taking annual leave. In addition, a temporary car park has been created for Scottish Water employees on Scottish Water’s land behind Tusitala Pavilion.
Please click here (pdf) to view the phasing of the trial pit work.

